NAVWARN details

ID NW-P-0169-25
Date 2025-02-01 04:20 UTC To 2025-03-01 02:00 UTC
Status Published
Title Marine works - Restriction to navigation
Areas Fraser River - North Arm
Categories Wharf Construction
Description

North Arm of Fraser River, upstream and downstream of the CN Lulu Island Rail Bridge, at Piers #27 (49 10.991N 122 59.263W), and at the Bents #25 to #7 of the East Approach Structure.

Work includes removal of Debris and installation of Piles and Work Platforms.

Hours of operation from 1500UTC to 0200UTC, Monday through Saturday, February 1 to March 1.

North Channel Closure during the East Approach Strrcture Works. 

Vessels monitoring VHF channels, 16, 71, and 74.

 

Position 49° 10.991'N 122° 59.263'W
Charts 3490(WGS84), 3491(WGS84)

Related links

Date Modified: